Al-Ju'aymah NGL Fractionation Plant (JNGLF) is a gas fractionation project in the Kingdom of Saudi Arabia. Established in 1978, it was inaugurated in 1980, due to the need for plants that could keep pace with production developments following the establishment of the main gas network. It is one of the main components of the network that works to collect and process gas.

Construction and expansion of Al-Ju'aymah Gas Plant

Construction of the first and second fractionation modules at JNGLF Plant began in 1978, with a capacity of 528,000 bbl of natural gas liquids per day. The third module was established in 1999, increasing the plant's capacity to approximately 790,000 bbl per day. In 2009, a fourth fractionation module was commissioned, increasing the plant's capacity to 1.1 million bbl of gas per day, making the gas fractionation plants in Al-Ju'aymah an important part of the Saudi petrochemical industry and the global economy.

Electrical power at Al-Ju'aymah Gas Plant

JNGLF Plant consists of five operating zones, in addition to a cogeneration module for electricity. To achieve self-sufficiency in electricity for Al-Ju'aymah Gas Plant, two cogeneration modules were built and began operating in 2006. The cogeneration plant exports up to two hundred MW of electricity to the network.

Feeding Al-Ju'aymah Gas Plant

JNGLF Plant is fed from several Saudi Aramco gas projects. It receives ethane plus from the gas plants of Shedgum, Al-Uthmaniyah, Al-Hawiyah, Al-Khursaniyah, and Shaybah gas plant. Additional propane plus comes from Abqaiq and Berri gas plants, as well as from Al-Qatif, Abu Safah, and Al-Khursaniyah plants.

Al-Ju'aymah Gas Plant productivity

JNGLF Plant has a fractionation capacity of approximately 1.1 million bbl per day, producing ethane, propane, butane, and heavy gases. This makes it one of the largest gas fractionation projects in the world, following the expansion of its activities with the construction of a fourth fractionation module as part of Al-Hawiyah Gas Project.

Following the expansion in 2009, the total fractionation capacity at JNGLF Plant increased to 815,000 bbl per day, by adding capacity to fractionate more than 270,000 bbl per day of natural gas liquids containing ethane and heavier components. In addition, the fractionation capacity of natural gas liquids containing propane and heavier components was increased by one hundred thousand bbl per day.

Transporting products of Al-Ju'aymah Gas Plant

Most of the propane and butane produced by the fractionation modules at JNGLF Plant is transported to Al-Jubail, while the remaining quantities are cooled before being transferred to storage tanks, each with a capacity of six hundred thousand bbl. The propane and butane stock is then pumped to the artificial island for export to international customers.

Pentane and natural gasoline products are pumped from JNGLF Plant to Al-Jubail, with the remainder pumped to the Ras Tanura terminal for export to international customers. In addition, hexane plus is pumped to Saudi Chevron Phillips Company in Al-Jubail.

Al-Ju'aymah Gas Plant achievements

Al-Ju'aymah Gas Plant has achieved excellence and safety milestones, receiving the 2019 Safety Excellence Award from GPA Midstream Association for its contribution to safety in transportation and processing, achieving 4.5 million man-hours without lost-time injuries.